Name of Contractor: 3D Construction
Award Sum: $26,963,800
Date of Award: 2025-04-25
Duration: 6 Months (2025-05-02 to 2025-11-02)
Status: Awaiting BOQ
Location: Shulinab Village, South Central Rupununi
Name of Contractor: Okemmy Jarvis
Award Sum: $14,000,000
Date of Award: 2025-03-06
Duration: 3 Months (2025-03-13 to 2025-06-13)
Status: 90% Works Ongoing
Location: Katu'ur Village, South Central Rupununi
Name of Contractor: Synergy Supplies & Services
Award Sum: $13,952,840
Date of Award: 2025-04-25
Duration: 3 Months (2025-05-02 to 2025-08-02)
Status: 20% Works Ongoing
Location: Quarrie Village, Central Rupununi
Name of Contractor:
Award Sum:
Date of Award:
Status: To be tendered
Location: Karasabai Village, South P/K Rupununi
Name of Contractor: Paul D' Aguiar
Award Sum: $13,225,200
Date of Award: 2025-04-25
Duration: 3 Months (2025-05-02 to 2025-08-02)
Status: 30% Works Ongoing
Location: Lethem, Central Rupununi