Name of Contractor: Javan Torres
Award Sum: $2,992,376
Date of Award: 2025-03-06
Duration: 2 Months (2025-03-13 to 2025-05-13)
Status: 100% Completed
Location: Fly Hill Village, Central Rupununi
Name of Contractor: Hilbert Lawrence
Award Sum: $6,000,000
Date of Award: 2025-03-06
Duration: 2 Months (2025-03-13 to 2025-05-13)
Status: 80% (Works Ongoing)
Location: Baishaizon Village, Deep South Rupununi
Name of Contractor: Shavez Hendricks
Award Sum: $6,000,000
Date of Award: 2025-04-01
Duration: 3 Months (2025-04-07 to 2025-07-07)
Status: 10% Mobilization
Location: Parabara Village, Deep South Rupununi
Name of Contractor: Royston Fitzpatrick
Award Sum: $7,000,000
Date of Award: 2025-04-01
Duration: 3 Months (2025-04-07 to 2025-07-07)
Status: 30% Works Ongoing
Location: Koneshen Village, Deep South Rupununi
Name of Contractor: Newton Pugsley
Award Sum: $2,918,500
Date of Award: 2025-03-06
Duration: 2 Months (2025-03-13 to 2025-05-13)
Status: 60% (Works Ongoing)
Location: Baitoon Village, South Central Rupununi